February 2025 status report on LAX Automated People Mover. 91.7% as of 2/22/25, +0.1% since 1/25/25. Percentages are misleading (change orders distort progress). Contractor added 28 days to estimated service date, now 2/9/26 instead of 1/12/26. emma.msrb.org/P11833966-P1...

mar 28, 2025, 3:50 pm • 13 0

Replies

avatar
ljwalsh.bsky.social @ljwalsh.bsky.social

That’s also 28 days since the last report, so a 1:1 on passed time : delayed time… not great

mar 28, 2025, 10:04 pm • 0 0 • view
avatar
Taylor Cardenes-Moore @tmoore4000.bsky.social

Is this just to spite LAWA?

mar 28, 2025, 4:02 pm • 1 0 • view