🚧 Big progress this week as the new 400-seat addition at the Sardis Secondary School in Chilliwack begins to take shape! 🚧

image image image image
may 19, 2025, 5:57 pm • 15 4

Replies

avatar
Bowinn Ma @bowinnma.bsky.social

Highlights include: -Roof beams now in place above the Music room and new Drama room -3 truckloads of Cross-laminated timber (CLT) arrived: 69 of 298 pieces installed so far -New weight room construction started as part of mini gym expansion

image image image image
may 19, 2025, 5:57 pm • 7 0 • view