no, you are releasing funding annually- so contracts will back off to that. megaproject contracts are really, and I mean *really*, complicated with tens to hundreds of suppliers

aug 6, 2025, 1:25 pm • 6 0

Replies

avatar
Fin @fintasm.bsky.social

How do other countries plan & fund this stuff? (I’m thinking of the crazy long tunnels under the mountains in Norway - that has to have been a hugely complex project - but many other countries’ rail infrastructure works better than the UK)

aug 6, 2025, 3:58 pm • 0 0 • view
avatar
Mark Liversedge @liversedge.bsky.social

Lots of commercial mechanisms- shared risk/reward, milestone delivery payments, penalty clauses etc etc. All of which happen in the UK. The UK legislative and regulatory environment is not suited to scale, pace or uncertainty- all of which are challenges for megaprojects

aug 6, 2025, 4:38 pm • 1 0 • view
avatar
Fin @fintasm.bsky.social

Thank you

aug 6, 2025, 7:50 pm • 1 0 • view
avatar
Mark Liversedge @liversedge.bsky.social

this is what the government is actually doing to try and fix things- contrary to popular belief there are some smart people working there :) (not me, nothing to do with this) www.gov.uk/government/p...